The work was completed without stopping the building's operation
Focus: soil stabilization foundations of a private house
Technology: Deep Stabilization & Slab Lifting
Year: 2015
Reason for treatment:
cracks on the blind area surface;
subsidence of the blind area;
zamokanie basement walls.
Problem: as a result of the survey of the ground by dynamic sensing, voids up to 10 cm were found under the blind area, and the foundation backfill soil was loose.
Goal: stabilization of the ground at the base of the blind area around the perimeter of the house with a basement.
Completed works:
filling of cavities under the blind area and along the basement walls;
compaction of backfill soil to the basement floor level;
stabilization of light pits;
leveling of the blind area.
Methods used: Deep Stabilization, Slab Lifting.
Scope of work: 80.2 m2 of blind area slabs.
ORDER PROJECT SELECTION AND CONSULTATION
If you can't findan object or situation similar to yours in your portfolio on the website, then order a selection of a project that meets your requirements with a detailed description or with the advice of a geotechnical engineer.